The installation of new plumbing requires strict adherence to the angles of inclination of the sewer pipes and the perfect sealing of each node. Ignoring the bowl alignment rules leads to uneven load distribution, the formation of microcracks in the porcelain and flooding of the bathroom.
Self-installation of the floor compact allows you to save your budget and control the quality of the valve assembly. Analyzing the technical regulations will help to fix the product and connect communications without calling a qualified plumber.
Dismantling the old bowl and preparing the base
The disposal of spent equipment begins with the complete shut-off valves on the cold water riser. The remaining liquid from the tank is drained, and the remaining volume from the water seal is scooped out with a sponge to prevent leaks onto the tile.
Unscrewing rusty mounting bolts often requires the use of WD-40 penetrating lubricant or cutting hardware with a metal hacksaw. After removing the old bowl, it is necessary to clean the mouth of the sewer pipe from petrified cement and remnants of the old rubber cuff.
The preparation of the floor covering includes removing traces of old sealant and checking the plane with the building level. If the tile has height differences of more than two millimeters, it will be necessary to install a compensating gasket to eliminate backlash of the ceramic base.
The cleaned sewer pipe is temporarily closed with a plastic plug or a tight bag to block toxic fumes. The floor surface is degreased with a technical solvent to ensure maximum adhesion of the silicone compound at the final stage.
Connecting the outlet and fixing the base
The choice of the connecting element depends on the geometry of the sewer outlet and the type of outlet of the installed faience. Rigid fan tubes ensure reliable drainage, and the reinforced corrugation forgives axis displacements up to 15 centimeters.
The integration of the adapter sleeve into the socket requires the pre-application of a layer of sanitary silicone on the sealer lobes. The step-by-step positioning algorithm for a floor product consists of a strict sequence of actions:
- connecting the outlet to the corrugation to check the connection geometry;
- tracing the contour of the support area with a flushable marker on the tile;
- marking of drilling points through the fixing eyelets;
- pulling the bowl aside to free up the work area;
- drilling tiles with a spear-type impact drill.
The plastic dowels are hammered into the holes with a rubber mallet to avoid chipping on the glaze tiles. The floor contour is filled with a transparent sealant, after which the faience is returned to the marked position and pressed tightly to the floor.
The brass screws are tightened with a torque wrench or manually, alternating between the left and right sides to evenly distribute the pressure. Excessive force during fixing is guaranteed to cause the ceramic bed to split.
Assembly and adjustment of drain fittings
The flushing mechanism is mounted inside the tank with the mandatory use of standard silicone gaskets that do not require additional coating with sealant. The shut-off valve is centered relative to the drain hole to prevent misalignment of the stem and jamming of the buttons.
The tank is connected to the main bed through a thick porous gasket that compensates for the thermal expansion of the materials. Before the final tightening of the mounting wings, the craftsmen recommend checking the correct operation of the mechanism according to the checklist:
- adjusting the height of the float to adjust the filling volume;
- checking the freewheel thrust of the filler valve;
- calibration of the mechanism of small and large water discharge;
- visual inspection of the clamping nut of the lower inlet;
- monitoring the position of the overflow safety tube.
The cold water supply line is supplied with a flexible reinforced hose with cap nuts. When screwing the fitting onto the plastic thread of the filler valve, it is forbidden to use linen or fum tape, a factory rubber ring is sufficient.
The water supply valve opens by a quarter turn to smoothly fill the tank and eliminate water hammer. At this stage, the tightness of the lower joint of the tank is monitored and the float switch is activated when the operating mark is reached.
Final testing and commissioning
Hydraulic tests of the assembled circuit are carried out by three complete water discharges with an interval of five minutes. Dry toilet paper applied to all the joints allows you to instantly identify microscopic smudges.
The detection of moisture at the junction of the corrugation and faience requires dismantling the assembly, drying the parts with a hair dryer and reassembling with the addition of polyurethane glue. If the tank mounting bolt leaks, it is enough to tighten the nut one turn with a horn wrench.
After successful completion of the tests, the perimeter of the support area is decorated with white sanitary silicone, which blocks the ingress of moisture under the bed. The installation of the microlift seat through the eccentric bushings completes the installation process of the plumbing appliance. Discover how to maximize your betting potential on one of the world's largest international platforms. The journey begins with registration, but the real catalyst for exceptional rewards is using a 1xbet promo code which unlocks a 100% deposit bonus up to $/€130 for sports betting or a casino package of €1950 with 150 free spins. This powerful combination provides an immediate boost far exceeding standard offers. Whether you are a cricket enthusiast, football fanatic, or casino lover, this promotional tool gives you a significant advantage. New members can start their adventure excessive personal risk.